Tuesday, February 18, 2014

Procurement & Tendering - Lesson 04

Advantages of Design & Build Contracts
·         Single point contract, one stop – shop approach
·         Design risks passed to the contractor
·         Speedy execution
·         Contractor’s specialist knowledge – more efficiency (design and experience together)
·         Specialist scopes
·         Minimum variations
·         More cost certainty
·         Minimum supervision cost  
·         Opportunity for innovation
·         Minimum risk of claims
·         Minimum administration for Client  
 Disadvantages of Design & Build Contracts
·         Designed by contractor, Employer has no control on the quality of the design
·         If variations occur, cost will be high
·         Difficulties in evaluating different designs  
·         Danger of design-build become build-design !
·         Limited pool of qualified design – builders
·         Lack of design brief may create more risks
·         Quality Assurance and Quality Control in contractor’s hands

·         Procurement of D&B Contract is more costly  

Tuesday, February 11, 2014

Procurement & Tendering - Lesson 03

Picture Credit:mi9.com 

Advantages & disadvantages of ‘Traditional Path’

Using this traditional procurement approach, the client contracts with an architect or an engineer to carry out the design; the client also enters into a separate contract with a contractor who carries out the building works.
Following are the advantages and disadvantages of traditional Procurement Route in the Client’s point of view:
Advantages
·         Client has the full control of the design. Consultants are directly reporting to the Client  
·         Since the control of the design with Client, quality of the project also could be controlled by the client
·         If the work is completely designed, cost certainty is guaranteed
·         This procurement route is more familiar to the contractors and consultants, hence less risks premiums involved in pricing
Disadvantages  

·         If the design is not completed, there will be variations which will lead to lose of control of cost certainty

·         In determining defects, it will be difficult to identify the defect, whether due to poor design or due to poor workmanship

·         Design risks to bear by Client, hence Contractor will not take and design responsibility

·         Contractor may focus the lump sum price to win the tender and as a result, more claims will be raised

·          Since the complete design is a prime requirement for a perfect ‘traditional procurement path’, delays to start the project is common.
We will discuss the above advantages and disadvantages in selecting of a procurement route for a particular type of project in upcoming sessions. 

OQSC

Saturday, February 8, 2014

Procurement & Tendering - Lesson 02


What are the factors to be considered in selection of a procurement route?
 Now you are ready to decide which procurement route to be selected for your project. It is important to do an analysis before taking the decision. In this analysis following factors to be considered:
1.       Risks involved
What are the risks you can take and how much? This is the question you should answer before the analysis. What are the resources available with you to handle this project? Do you have experience in handling these projects? Money is not enough to manage a project.
Construction is the most risky legal business in the world. There are various risks types involved in construction sector:
a.       Legal & regulatory risks
b.      Environmental risks
c.       Economical risks
d.      Contractual risks
e.      Management risks
f.        Health & Safety risks
g.       Risks of inflations
h.      Quality control risks
i.         Design risks
j.        Financial risks   
So it is a big decision! When you select your procurement route you have to analyze how you manage all above risks.  Can you take all risks? Or you wish to pass some of the risks? Deciding a suitable procurement route will depend on your decision on taking, passing or sharing of risks. If you are capable you can take the risk. If any other party could take the risk completely you can pass the risk. Some of the risks you can share with other parties.  We will discuss each procurement path in the terms of sharing risks.
2.       Project size and complexity
It is important to assess the size of your project before deciding the procurement route. Further, your project may be very complex, for example a mixed used development including a public leisure facility. How many packages involved? Infrastructure, enabling works, buildings, water parks, rides, landscaping, sub stations, sewerage treatment plants, chilled water plants and many more..! Can you manage this complexity? Do you have resources? Experience?
3.       Quality
How much the level of quality impacts your decision? Is quality one of your prime requirements?   What kind of a building you are going to procure? You may need to deliver a 5 star hotel. So you may want to have world best finishes in your hotel. You may want to change the design of finishes as the project goes on, because you want latest updated designs in your hotel. So it is good to have the control of the design with you.  If you are going to build a workshop, it may not be the case!

4.       Time
When you need to complete this project? Time is money! Sometimes, you may have committed to investors or operators to deliver this project on a particular date. The speed of the construction or an early start of the project may be very important.  May be you can start the construction of some parts while the design of other parts are in progress to save overall time!

5.       Cost
How much money you have to construct this project? Do you have unlimited budget or limited budget? How much certainty of cost you are expecting? Can you go for unlimited variations? End of the day, your ultimate goal is doing business and earn profits using the buildings or other structures of this project. So the income generates from this project and the expenditure of the project matters!  

We will discuss how each procurement route help us in most appropriate way in the view of meeting the requirement of mitigating the risks and achieving objectives of the project, in the terms of quality, cost & time.



OQSC Publication

Tuesday, February 4, 2014

Procurement & Tendering - Lesson 01

Good day for everybody,

Having APC interviews on April 2014, we decided to refresh our candidates knowledge on several key areas on APC process outline.

From today, we will start to study Procurement and Tendering in this spot.

Today we will study about the basics of procurement, i.e. why? And How?  

What is Procurement?

In the construction industry procurement is a process that includes:

1.       Determining the objectives of the project – Traditionally, Cost, Quality and Time

2.       Setting the contractual frame work – working arrangement to meet above objectives

3.       Setting the selection and tender process – to obtain best price and value for money

4.       Inviting tenders

5.       Awarding

How you determine your project objectives?

Determining project objectives depend on your requirements. Project requirements are different project to project. For example, you are planning to build a 5 star hotel. What is your prime objective?

A 5 star hotel, of course, you require 5 star quality! To maintain this quality, will you allow others to decide on the quality? Definitely not! Then what you will do? Can you design? May be or maybe not, but if not, you can appoint a designer!

Hence, you will prefer traditional path (design by Employer) if you are ok with funds and time! What are the disadvantages of traditional path? Time? Cost?

Even if you appoint a designer, if project is complicated, can you manage?

Let’s start to study! 

OQSC                                                                                                                        T062-201402-01

Contract law

Article 273

Force Majeure in UAE Civil Code

In contracts binding on both parties, if force majeure supervenes which makes the performance of the contract impossible, the corresponding obligation shall cease, and the contract shall be automatically cancelled.

A force majeure event excuses the effected party from continuing to perform its obligation