Quantum meruit and its scope

Quantum meruit and its scope

The basic principle under English law for claims under quantum meruit is that the employer will have a duty to pay the fair value of or, reasonable remuneration for, the work performed. ADAM WEBSTER* compares the provision with the UAE Civil Code.
Quantum meruit entitlements arise most commonly in construction cases where there is no contract but work is undertaken in circumstances where it is clearly not being done for free.

In Latin, the phrase means “what the job is worth” and in essence, it allows a person to recover the value of work done or services performed in circumstances where he has conferred a benefit on someone else which justice requires should be repaid.
A typical quantum meruit claim might arise where work starts whilst the parties are negotiating contract terms but ultimately the parties have not agreed on the applicable rate that is to be paid to the contractor or fail to agree any contract at all.
Alternatively, where the work that has been carried out by a contractor with the employer’s consent or upon his instruction is so different from the scope of work envisaged in the original contract that a new contract has effectively been formed, the contractor may be entitled to claim a quantum meruit for the additional work done.
The law will not deny the contractor an entitlement to payment, and the basic principle in English law is that the employer will have a duty to pay the fair value of or, reasonable remuneration for, the work performed. Issues will inevitably arise, however, as to the appropriate basis for valuation.
It is often thought that quantum meruit valuations are highly advantageous to contractors and that invariably they will open the door to “cost plus” entitlement, that is the net cost of labour and materials used plus a sum for overheads and profit. In truth, there is a great deal of case law on quantum meruit with a range of different approaches having been taken. As HHJ Hicks held in Serck Controls v Drake & Scull Engineering Limited (2000) 73 ConLR 100:
“A quantum meruit claim may …arise… across a spectrum which ranges at one end from an express contract to do work at an unquantified price, which expressly or by implication must be a reasonable one, to work (at the other extreme) done by an uninvited intruder which nevertheless confers on the recipient a benefit which, for some reason, such as estoppel or acquiescence, it is unjust for him to retain without making some restitution to the provider … At the first end of the spectrum … the measure should clearly be the reasonable remuneration of the claimant; at the other, it should be the value to the defendant. In between there is a borderline, the position of which may be debateable.”
Clearly, this is an area of the law where judges in English courts have some discretion and results are by no means predictable. Indeed, the recent case of ERDC Group Limited v Brunel University (2006) 109 ConLR 114 usefully highlights the inherent uncertainties and risks which abound when contractors are entitled to be paid on a quantum meruit basis.
In short, ERDC successfully tendered for the design and construction of a new sports facility at Brunel University’s Uxbridge campus, but a delay in obtaining planning permission meant that Brunel had to instruct ERDC to commence work under a letter of intent.
This letter of intent was relatively lengthy and detailed and Brunel agreed to pay for any work that was done on the basis of certain valuation rules (which were to apply to the contract when signed). The letter authorised work to proceed for a stipulated period of time within which a formal contract was to be executed. Three more letters were to follow, each one extending further this deadline. During this period, ERDC had applied for payment on the basis of its tender rates and prices and applying JCT principles. After the expiry of the last letter of intent, no formal contract was in place, but ERDC continued to work.
In this case, the judge was satisfied that all the usual requirements for a contract were present until the expiry of the last letter (that is September 1, 2002) and so, as there had been a contract until then, ERDC was entitled to be paid in accordance with rates and prices determined under the valuation rules that had been incorporated into that contract.
From September 1, 2002 onwards, however, the contract was found not to apply, and so ERDC was entitled to be paid reasonable remuneration for the benefit that the university had received.
In assessing what would be a fair and reasonable sum, the judge agreed with a comment made by Brunel’s quantum expert that “a price or rate that was reasonable before September 1, in my opinion, does not become unreasonable after September 1 simply because the authority in the letter of appointment expires”.
The fact that ERDC’s tender was shown to have been commercial and close to others supported the conclusion that continuing to use ERDC’s rates and prices, in many instances, were fair. For certain other items, however, where works had been prolonged beyond the period contemplated by the rates and additional costs had been incurred by ERDC as a result, or if it were appropriate to do so under the valuation rules, the Judge held that “cost plus” should be the appropriate valuation method.
As this case illustrates, under English law the position is far from being clear cut and cost plus entitlement should certainly not be assumed as a given by the contractor. By comparison, therefore, the question presents itself whether the UAE law contains, within its codified civil system, any provisions that address the notion of quantum meruit in a more straightforward manner.
Article 888 of the UAE Civil Code (“the Code”) applies where the parties have not agreed remuneration and the issue of a contractor’s entitlement to a reasonable remuneration arises. In this regard, Article 888 provides that, if the consideration for the work is not specified in a contract, the contractor is entitled to ‘fair compensation’, together with the value of the labour and materials he has provided (that is a cost plus approach).
Article 887 of the Code provides that a contractor may not demand any increase over a contractually agreed lump sum. Although the contractor assumes the risk in such a case for any cost overrun in carrying out the agreed lump sum works, it should not necessarily preclude a contractor from claiming payment on a cost plus basis for authorised works which fall outside the original scope of lump sum works.
However, Article 887 then goes on to provide that if any variation or addition is made to the scope of works with the consent of the employer, the existing agreement with the contractor must continue to be observed.
Under UAE law, therefore, an entitlement to an increase price for lump sum contracts is generally denied, subject only to variations or additions, the pricing of which should be assessed in the context of the overall work carried out. In the event that the employer instructs work that is out of scope and there are no applicable rates and prices under the contract, the contractor would be entitled to claim compensation by way of Article 888 and claim ‘fair compensation’, presumably on a cost plus basis.

Sunday, February 16, 2014

FIDIC Conditions Explained - Lesson 03

Engineer’s Role – 1987 v 1999 Red Book
FIDIC 1987-Fourth Edition-Clause 2.1-Engineer’s Duties and Authority
(a)  The Engineer shall carry out the duties specified in the Contract.

(b) The Engineer may exercise the authority specified in or necessarily to be implied from the Contract, provided however that if the Engineer is required, under the terms of his appointment by the Employer, to obtain the specific approval of the Employer before exercising any such authority, particulars of such requirements shall be set out in part II of these Conditions. Provided further that any requisite approval shall be deemed to have been given by the Employer for any such authority exercised by the Engineer.
(c)  Except as expressly stated in the Contract, the Engineer shall have no authority to relieve the Contractor of any of his obligation under the Contract.
FIDIC 1987-Fourth Edition-Clause 2.6-Engineer to Act Impartially
Wherever, under the Contract, the Engineer is required to exercise his discretion by:
(a)  giving his decision, opinion or consent
(b) expressing his satisfaction or approval
(c)  determining value, or
(d) otherwise taking action which may affect the rights and obligations of the Employer or the Contractor
he shall exercise such discretion impartially within the terms of the Contract and having regard to all the circumstances. Any such decision, opinion, consent, expression of satisfaction, or approval, determination of value or action may be opened up, reviewed or revised as provided in Clause 67.    
FIDIC 1999-First Edition-Clause 3.1-Engineer’s Duties and Authority
The Employer shall appoint the Engineer who shall carry out the duties assigned to him in the Contract. The Engineer’s staff shall include suitably qualified engineers and other professionals who are competent to carry out these duties.
The Engineer shall have no authority to amend the Contract.
The Engineer may exercise the authority attributable to the Engineer as specified in or necessarily to be implied from the Contract. If the Engineer is required to obtain the approval of the Employer before exercising a specified authority, the requirements shall be as stated in the Particular Conditions. The Employer undertakes not to impose further constraints on the Engineer’s authority, except as agreed with the Contractor.
However, whenever the Engineer exercises a specified authority for which the Employer’s approval is required, then (for the purposes of the Contract) the Employer shall be deemed to have given approval.
Except as otherwise stated in these Conditions:
(a)  Whenever carrying out duties or exercising authority, specified in or implied by the Contract, the Engineer shall be deemed to act for the Employer;
(b) the Engineer has no authority to relieve either Party of any duties, obligations or responsibilities under the Contract; and
(c)  any approval, check, certificate, consent, examination, inspection, instruction, notice, proposal, request, test, or similar act by the Engineer (including absence of disapproval ) shall not relieve the Contractor from any responsibility he has under the Contract, including responsibility for errors, omissions, discrepancies  and non-compliances.
What is the major difference between 1987 and 1999 red book regarding this clause?

According to 1987 Red Book, Engineer has to cat impartially. But according to the FIDIC Red Book 1999 Engineer shall be deemed to act for the Employer. According to 1987 Red Book Engineer may review his determinations as provided in clause 67 (settlement of disputes). Then who will take over such duties towards settlement of disputes as per 1999 Red Book? Read clause 20 which states regarding Dispute Adjudication Board (DAB). We will discuss this in future sessions.

Monday, February 10, 2014

FIDIC Conditions Explained - Lesson 02

We will discuss the most important clauses of FIDIC Red Book 1987 and 1999 in this column.

FIDIC Red Book 1987-Fourth Edition

Clause 5.2-Priority of Contract Documents
The Several documents forming the Contract are to be taken as mutually explanatory of one another, but in case of ambiguities or discrepancies the same shall be explained and adjusted by the Engineer who shall thereupon issue to the Contractor instructions thereon and in such event, unless otherwise provided in the Contract, the priority of the documents forming the Contract hall be as follows:
1.  The Contract Agreement (If completed);
2.  The Letter of Acceptance;
3.  The Tender;
4.  Part 1 of these conditions and
5.  Any other document forming part of the Contract



FIDIC Red Book 1999-First Edition
Clause 1.5-Priority of Documents
The documents forming the Contract are to be taken as mutually explanatory of one another. For the purposes of interpretation, the priority of the documents shall be in accordance with the following sequence:

a)       the Contract Agreement (If any),
b)       the Letter of Acceptance,
c)       the Letter of Tender,
d)       the Particular Conditions,
e)       these General Conditions,
f)        the Specification,
g)       the Drawings, and
h)       the Schedules and any other documents forming part of the Contract.
If an ambiguity or discrepancy is found in the documents, the Engineer shall issue any necessary clarification or instruction.
What are the other documents? Following are some of other documents which we could evidence frequently:  
a.       Post tender correspondence
b.      Minutes of the post tender meetings –
c.       Appendix to Tender (if not a part of Tender as mentioned above)
Post tender correspondence and minutes of meetings may be has a higher priority than other documents Care should be taken regarding the Appendix to Tender which the contractor has used as a base of his price. There are around 30 clauses of conditions of contract which reflect in Appendix to Tender.
As a conclusion there is no much difference between 1987 and 1999 Red Book in this clause.
Ambiguity = Ambiguity means that what a thing is, is not clear.
Discrepancy = Discrepancy is an illogical or surprising lack of compatibility or similarity between two or more facts.
Similar words:

inconsistency, difference, disparity, variance, variation, deviation, divergence, disagreement, dissimilarity, dissimilitude, mismatch, lack of similarity, contrariety, contradictoriness, disaccord, discordance, incongruity, lack of congruence, incompatibility, irreconcilability, conflict, opposition More.

Saturday, February 8, 2014

FIDIC Conditions Explained - Lesson 01

Dear Members,

As we promised we are starting the FIDIC Condition Clauses explained lessons series from today.

FIDIC Rainbow suite

FIDIC is the French acronym of International Federation of Consulting Engineers. It was formed in 1913 by 3 national associations of consulting Engineers. Now it has 86 members of national associations.
FIDIC has forms for following agreements between:
·         Employer and Contractor (designed by Employer)
·         Client and Consultant
·         Joint ventures between consultants
·         Sub consultant agreements
·         Representative agreements
FIDIC Employer/contractor agreement was issued in 1957. From then there were several editions of various types of forms.
FIDIC issued three contracts for major works;

Red Book – Conditions of Contracts for works designed by the Employer, also known as the ‘construction contract’.  

Orange Book – Design & Build Projects

Yellow book – Conditions of contract for plant & design-build for electrical & mechanical plant and for building & engineering works designed by the contractor, also know as the Plant, Design & Build contract.

Silver Book – Conditions of contract for EPC/Turn Key projects also known as the EPC/Turnkey contract (EPC = Engineering, Procurement and Construction)
Other FIDIC issued contracts

Green Book – short form of contract

White Book – Contract between Client and Consultant

Pink Book – Contract for Multilateral Development Bank Harmonized version of Red Book

Gold Book – Design Build and Operate contracts

We will explain the important clauses of FIDIC 1987 and 1999 versions in detail in our future lessons.

OQSC

Contract law

Article 273

Force Majeure in UAE Civil Code

In contracts binding on both parties, if force majeure supervenes which makes the performance of the contract impossible, the corresponding obligation shall cease, and the contract shall be automatically cancelled.

A force majeure event excuses the effected party from continuing to perform its obligation