Wednesday, February 12, 2014

Methods of Measurements - Lesson 03

NRM (New Rules of Measurement) BY RICS

The New Rules of Measurement (NRM) are published by the Royal Institute of Chartered Surveyors (RICS) Quantity Surveying and Construction Professional Group. They provide a standard set of measurement rules for estimating, cost planning, procurement and whole-life costing for construction projects. Adopting a standard methodology such as NRM facilitates consistency and benchmarking and helps avoid disputes.
NRM1: Order of cost estimating and cost planning for capital building works.
NRM 1 was first published in February 2009 (as NRM Order of cost estimating and elemental cost planning). Now in its second edition, it provides guidance on the quantification of building works in order to prepare order of cost estimates and cost plans as well as approximate estimates. It also includes guidance about quantifying wider costs such as preliminaries, overheads and profit, risk allowances, and inflation.
NRM2: Detailed measurement for building works.
NRM2 is a new document that was published in April 2012. It became operative on 1 January 2013 and replaced the Standard Method of Measurement, seventh edition (SMM7) on 1 July 2013.NRM2 establishes detailed measurement rules allowing the preparation of bills of quantities, quantified schedules of works and schedules of rates in order to obtain tender prices. Guidance is also provided on the content, structure and format of bills of quantities.
NRM3 - Order of cost estimating and cost planning for building maintenance works.
NRM3 is currently under development. It is intended to allow the quantification and description of maintenance works. It will be used for initial order of cost estimates, general cost plans and asset-specific cost plans. It will also provide guidance on procurement and cost control.
NRM3 will also offer guidance about the measurement of other items associated with maintenance works that are not included in work items.

Tuesday, February 11, 2014

Procurement & Tendering - Lesson 03

Picture Credit:mi9.com 

Advantages & disadvantages of ‘Traditional Path’

Using this traditional procurement approach, the client contracts with an architect or an engineer to carry out the design; the client also enters into a separate contract with a contractor who carries out the building works.
Following are the advantages and disadvantages of traditional Procurement Route in the Client’s point of view:
Advantages
·         Client has the full control of the design. Consultants are directly reporting to the Client  
·         Since the control of the design with Client, quality of the project also could be controlled by the client
·         If the work is completely designed, cost certainty is guaranteed
·         This procurement route is more familiar to the contractors and consultants, hence less risks premiums involved in pricing
Disadvantages  

·         If the design is not completed, there will be variations which will lead to lose of control of cost certainty

·         In determining defects, it will be difficult to identify the defect, whether due to poor design or due to poor workmanship

·         Design risks to bear by Client, hence Contractor will not take and design responsibility

·         Contractor may focus the lump sum price to win the tender and as a result, more claims will be raised

·          Since the complete design is a prime requirement for a perfect ‘traditional procurement path’, delays to start the project is common.
We will discuss the above advantages and disadvantages in selecting of a procurement route for a particular type of project in upcoming sessions. 

OQSC

Contract law

Article 273

Force Majeure in UAE Civil Code

In contracts binding on both parties, if force majeure supervenes which makes the performance of the contract impossible, the corresponding obligation shall cease, and the contract shall be automatically cancelled.

A force majeure event excuses the effected party from continuing to perform its obligation